Connecticut's construction sector requires strict adherence to mechanics lien recording deadlines. MyCrewTracker provides Connecticut contractors with a centralized platform to manage project documents and track 90-day statutory deadlines.
Connecticut Certificate of Mechanic's Lien
Connecticut mechanics lien law contains rigid recording deadlines. Under Conn. Gen. Stat. § 49-34, any person who claims a mechanics lien must generally record a Certificate of Mechanic's Lien within 90 days after they have ceased to perform services or furnish materials.
Missing this deadline forfeits the right to claim a mechanics lien. By utilizing MyCrewTracker's Daily Reports, field supervisors generate a verifiable, date-stamped log of when work actually concluded, ensuring the back office never misses this 90-day window.
Connecticut Prompt Payment
For private construction contracts, Conn. Gen. Stat. § 42-158j mandates that an owner generally must pay the prime contractor within 30 days of receiving a proper invoice. Subcontractors must similarly be paid within 30 days of the contractor receiving payment.
To enforce these rights or defend against withholding claims, contractors must maintain flawless documentation. MyCrewTracker offers a secure cloud repository where Connecticut contractors can organize dated payment applications and disbursement records to prove statutory compliance.
❓ Frequently Asked Questions in Connecticut
When must a Connecticut Certificate of Mechanic's Lien be recorded?
Under Conn. Gen. Stat. § 49-34, a lien claimant must generally record the certificate within 90 days of their last day on the job.
What is the Connecticut Prompt Pay deadline for subcontractors?
Under Conn. Gen. Stat. § 42-158j, prime contractors and higher-tier subcontractors must generally pay lower-tier subcontractors within 30 days of receiving payment for their work.
Does MyCrewTracker calculate my 90-day lien deadline?
No. MyCrewTracker is a secure document storage platform. It helps you definitively prove your last day of work using Daily Reports, but you must manually calculate the 90-day deadline.
Official Legal Sources
-
Certificate of Mechanic's Lien Conn. Gen. Stat. § 49-34
Connecticut Mechanics Lien — A Certificate of Mechanic's Lien must generally be recorded within 90 days of ceasing to perform services or furnish materials.
-
Prompt Payment Act Conn. Gen. Stat. § 42-158j
Connecticut Prompt Pay — Owners must pay contractors within 30 days; contractors must pay subs within 30 days of receiving funds.